The Tough Jobs

We were recently awarded a project to provide oil recycling and forensic teardown and recycling of a 375,000 lb. transformer. This project presented many challenges as we were working with a short outage timeframe and removal from a very tight location. Here is the transformer prior to removal showing all of the overhead equipment and surroundings

Our experienced crews along with our innovative transformer removal methods and patented equipment allowed us to tear down the transformer on its existing pad saving the customer time and money in relocation.

The experience and teamwork of our transformer removal crews allows for a very methodical and seamless operation providing the safest and most efficient transformer recycling in the industry.

A-Line E.D.S. also provided the service to remove the retention wall from around the transformer which minimized the need for multiple contractors on site.

Clean up after transformer recycling is important in saving our customers time and money as well as eliminating any environmental hazard. A-Line E.D.S. protects all laydown areas and leaves the site in better condition that it was found.

This job was completed in less than 5 days and well within the allotted outage schedule. It is our mission to provide creative solutions to tough transformer removal projects in order to get repeat customer business for years to come.